Fire Station #1 Progress

Llano County ESD 5 Sunrise Beach Fire Department logo. A red Maltese cross with FD and an EMS symbol.

Great progress is being made on the Fire Station Renovation Project. The following is a detailed synopsis of progress to date:


Design


  • Necessary Structural Modifications complete - certified by Design Engineer (letter of completion on file)
  • Station Alerting Drawings finalized, contract awarded to APS, materials procured, rough-in wiring completed
  • Low Voltage Automation (integration of CAD, Wi-Fi, HDMI extenders, radio system COAX, Electronic Equipment Racks) drawings complete to enable Time & Materials approach for install
  • Issued Contract for Flatwork Design – concrete aprons & asphalt; to Bluebonnet Designers for ~$4,080 ($10,000 NTE previously approved by Board)


Construction Progress 

(had ~ 3 days of weather delays – ice storm) – crews currently working 6 to 7 days/week


  • Electrical rough-in complete and third-party inspection done (enables spray foam insulation application), temporary power to some permanent lights
  • Plumbing rough-in complete and third-party inspection done
  • Dorm Fire Sprinkler system installation complete and tested – seeking approval certificate from our Fire Marshal following his inspection.
  • 4 HVAC systems rough-in complete; truck bay heater installed (not in service yet); Kitchen Vent Hood (FS) Ordered and installation after sheetrock installation.
  • Apparatus Bay Wall (1 hour fire rated sheetrock) complete and finishing underway; 4-foot laminate lower section planned for protection of wall
  • Garage Door Openers – ordered and installed, 6 total, contract includes maintenance and updates on doors (seals, nylon rollers)
  • Suspended ceiling framework rough-in complete – will be leveled after all lights and ceiling panels installed
  • Fire Alarm System – pre-wiring completed
  • Exterior Windows installed, some minor trim work remaining
  • Exterior Doors remaining (Front and Patio) – due to arrive by Feb 25
  • All interior doors ordered – Will arrive early March
  • All fire rated doors and fire rated windows ordered; fire doors will arrive in ~ 1 week; windows delivery ~3.5 months (4 temporary covers installed)
  • VFD successfully leased 500-gal propane tank from 4T Propane at $1/yr
  • All plumbing fixtures ordered
  • Kitchen Cabinets and countertops ordered
  • Radio Tower ordered and delivered;
  • Spray foam Insulation contract awarded; started Feb 12, Finish Feb 19 (rock wool insulation for Fire Rated walls, and open cell insulation under gym floor)
  • Third-Party Inspections (5 are completed, some punch list items), next inspection is of Insulation.


Near Term plans

 

  • Complete Insulation scope of work, inspect by Friday Feb 20
  • Begin Sheetrock of interior
  • Commence interior Door insulation
  • Begin painting post sheetrock
  • Installation of Radio Tower & antennas, Truck Bay Fan (single), louvers & vent fans on trucks
  • Ordering interior flooring
  • Start Trim work for Plumbing, Electrical, Low Voltage Automation (incl COAX Cables), Fire Alarm Hardware, APS Fire Alert Hardware
  • Begin ordering of appliances, hardware for outfitting of station
  • Finalize design of flatwork – concrete & asphalt and bid by Feb 20. Target start of work by March 4 if possible
  • Title transfer of properties and lots initiated with Highland Lakes Title. Draft Title Commitment letter has been received, with closing scheduled for February 27th.


# # #

 


February 3, 2026
Sunrise Beach Fire Department Responds to Fatal Two-Vehicle Collision on FM 2900 
January 24, 2026
Texas A&M Forest Service Wildfire Risk Assessment for Local Area
January 24, 2026
Station One Construction Update
January 23, 2026
Winter Weather and Extreme Cold Warning!
January 19, 2026
Progress Being Made on Fire Station #1
January 6, 2026
FIRE STATION #1 RENOVATION UPDATE WITH SAFETY WARNING!
December 16, 2025
Llano County ESD #5 Receives Texas A&M Forest Service Equipment Grant
December 16, 2025
Commissioner Andy Spencer Resigns Post
Care Flight Helicopter
December 1, 2025
Hamilton EMS Utilizes Sandy Creek Helipad
October 16, 2025
SBFD/Llano ESD5 Awarded a Grant for a Large Brush Truck